GENERAL

From April 1994, Swindon 'B' Signalling Control Centre took control of the Didcot area, as part of the Didcot-Swindon resignalling scheme.

Standard BR multiple aspect signalling is in use, with Track Circuit Block working.

RUNNING LINES

Bidirectional working is provided for as follows:-
   
       Milton to Foxhall Junction:
           Down Main, Up Main and Relief Lines

       Foxhall Junction to Didcot East:
           Up Goods Loop/Platform 4/Up Relief
           Relief Line/Platform 3/Down Relief

Permissive working of trains of classes 1,2,3 and 5 is permitted on platform lines 3, 4 and 5 only, i.e. 2 trains may use the same platform. 

Freight trains and light engines may terminate or originate from Didcot Power Station, Milton Sidings, Didcot Yard, the Appleford ARC Sidings and the GW Society sidings. ECS workings may also run to and from Didcot Yard, Milton Sidings and the GW Society.

Trains entering Didcot Yard may use any of the 3 entrances. Trains leaving the Yard will use the appropriate exit, according to destination. 

Note that the scale used on the track diagram is not uniform.

PLATFORM CAPACITIES
   
         Platform         No. of Coaches (*)
   			 
            1                   18
            2                   19
            3                   13
            4                   13
            5                   13

(*) Reduce by 1 for each loco on loco-hauled trains.
    Double the resulting figure for freight trains, other than Cl.4.
    
    Note these capacities may differ a little from the prototype.

TRAIN REPORTING NUMBERS

     First Character (Train Class):

           1      Express Passenger  
           2      Ordinary Passenger       	
           3      Parcels  (Max. 90 mph+)  	
           4      Freight (Max. 65 mph+)      
           5      Empty Coaching Stock     	
           6      Freight (Max. 50-60 mph)    
           7      Freight (Max. 40-45 mph)    
           8      Freight (Max. 35 mph) 		
           9      Unfitted Freight  			
           0      Light Engine             	

     Second Character (Destination):
  
           A      Workings within Western Region
           B      Workings within Western Region
           C      Workings within Western Region
           F      Workings within Western Region
           E      Eastern Region
           M      London Midland Region
           O      Southern Region
           S      Scottish Region
           V      Western Region (from another Region)
           Z      Local Movements	        

Routing is as specifed in the Working Timetable. 

Light locos and empty coaching stock proceeding to/from a booked working may carry the headcode 0 or 5, followed by the last 3 characters of the train concerned.

MAXIMUM SPEED

Up & Down Main                            125 mph

Relief Lines:
    Steventon - Foxhall Junc               50 mph
    Foxhall Junc - Didcot East             70 mph
    East of Didcot East                   100 mph

Didcot Avoiding Lines (Up/Down)            70 mph
          
Oxford Lines (Up/Down):
    West of Didcot North Junction          90 mph
    Didcot North Junction                  40 mph
    East Curve                             25 mph
    To/from Plats 4/5 and Didcot Yard      15 mph
              
Didcot West Curve (Up/Down)                25 mph
          
Down Goods Loop                            25 mph

Power Station Reception Lines              25 mph              

Milton Sidings, ARC Sidings                15 mph          

Through Crossovers: 
    Didcot East, Moreton Cutting           70 mph
    Foxhall Junction - Up to Dn Main       40 mph
                     - other               25 mph
    Milton                                 50 mph
                               
Wrong direction movements                  20 mph
Propelling                                 20 mph